英語復(fù)習(xí):The earned value technique is a commonly used method of performance measurement.
The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. If a project’s Schedule Performance Index(SPI=EV/PV) value less than 1.0, it means that ( ).
A、the project is ahead of its planned schedule
B、less work was completed than was planned
C、the cost overrun for work completed
D、the cost under-run of performance to date
掙值技術(shù)是一種通用的績效測量方法。它將項(xiàng)目范圍、成本、進(jìn)度整合在一起,幫助項(xiàng)目管理團(tuán)隊(duì)評估項(xiàng)目績效。SPI值若小于1則表示實(shí)際進(jìn)度落后于計(jì)劃進(jìn)度。