試卷名稱 信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-3
考試中心《信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-3》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

Within an organization, office politics have negatively impacted previous projects, consuming large amounts of stakeholder time. What should the project manager do at the start of the project to ensure the politics do not affect the current project ?
A、Seek sponsorship from senior management.
B、 Recommend a new project manager with proven capabilities in dealing with politics.
C、 Hire a third party project manager to avoid the politics inside the organization.
D、 Let the stakeholders select the right project manager for the project.