The overall project plan is developed and approved. The project manager will formally declare the start of the project and present the summary of project milestones schedule to the stakeholders. What will the project manager do next ?
A、Send the project plan to the team members.
B、Schedule a weekly project review meeting.
C、Conduct a team building event.
D、Conduct a kick-off meeting with team members.