欧美性大战久久久久xxx|成人精品影院|市来美保av|亚洲一级国产,亚洲欧美在线看,亚洲欧美福利,香水电影在线观看完整版免费未删减

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學習 培訓課程
試卷名稱 2017年信息系統(tǒng)項目管理師最新英語模擬題(1)
考試中心《2017年信息系統(tǒng)項目管理師最新英語模擬題(1)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內容

Diagram shows the sequence of activities for project xyz and its duration, The project manager is asked to reduce the project duration by two weeks, None of the activities can be fast tracked. Activities A and F cannot be crashed; activity G can be crashed by two weeks; and all other activities can be crashed by one week.To meet the new project duration requirement, which of the following will the project manager decide to do?

A、Crash activity G

B、Crash activities C and D

C、Crash activities G and C and D

D、Crash activities G and F and C


相關試題

推薦文章
合作網站內容