欧美性大战久久久久xxx|成人精品影院|市来美保av|亚洲一级国产,亚洲欧美在线看,亚洲欧美福利,香水电影在线观看完整版免费未删减

軟題庫 移動(dòng)APP 掃碼下載APP 隨時(shí)隨地移動(dòng)學(xué)習(xí) 培訓(xùn)課程
試卷名稱 2017年信息系統(tǒng)項(xiàng)目管理師最新英語模擬題(3)
考試中心《2017年信息系統(tǒng)項(xiàng)目管理師最新英語模擬題(3)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

A project to implement a new system has trouble launching due to extensive and contradictory discussions regarding the project deliverables. The project manager leaves the company, and a new project manager is assigned to the task.What should be the first action for the new project manager?
A、Formalize the project management plan and communicate this to relevant stakeholders
B、Escalate to the project sponsor and request support in handling the ongoing discussions.
C、Develop a work breakdown structure and communicate this to all relevant stakeholders.
D、Formalize a project charter and request approval from the sponsor and key stakeholders.


相關(guān)試題

推薦文章