試卷名稱 2017年信息系統(tǒng)項目管理師最新英語模擬題(5)
考試中心《2017年信息系統(tǒng)項目管理師最新英語模擬題(5)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

At the beginning of a project, the project manager holds a risk workshop with the project team and the key customer stakeholders. After the workshop, they produce a matrix with several risks. Their probabilities, and impacts for the project. What type of risk analysis was performed in the workshop?
A、Qualitative risk analysis
B、Quantitative risk analysis
C、Categorization risk analysis
D、Delphi technique risk analysis