欧美性大战久久久久xxx|成人精品影院|市来美保av|亚洲一级国产,亚洲欧美在线看,亚洲欧美福利,香水电影在线观看完整版免费未删减

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學(xué)習(xí) 培訓(xùn)課程
試卷名稱 2017年信息系統(tǒng)項目管理師最新英語模擬題(6)
考試中心《2017年信息系統(tǒng)項目管理師最新英語模擬題(6)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

The project manager in the control quality product inspection process discovers that a product currently manufactured has a design defect that could potentially reoccur in the company’s future projects. The project manager known the problem can be solved with a minimal Stander change. What should the project manager do next?
A、Continue with the project as planed and leave the improvement for another project.
B、Recommend a standers update.
C、Update the quality management plan.
D、Wait until the next project manager’s meeting to notify other project manager of the problem.


相關(guān)試題

推薦文章
合作網(wǎng)站內(nèi)容